Kelso base progress - Dec 22

December 2022

Our new base is looking a lot closer to completion now that the doors and windows are in and the plant room's formed. We're hoping to move all of our kit in early in the new year.

There are however, three main things that need to happen before we can make the move.

The electric cable is installed and ready to connect but we need a supplier who’ll put in a meter and give us an account - not as easy as you’d expect as several suppliers have a hold on new contracts at present.)

Now that the network electric cable is connected to building, the entrances are soon to be tarmacked.

Some final adjustments will be completed by our groundwork contractor this week before Scottish Water finalise that connection.

 

So, once power, water and smoother access are in place, we're good to go!